Project number | AP15573950 |
Name of the project | Intelligent power grid analysis and control system |
Applicant | “Almaty university of power engineering and telecommunications named after G.Daukeev” Non-comercial JSC |
Grantee | «Center for Energy and Environmental Research (CEER)» JSC |
Private Partner | “Mangistau Regional Electricity Network Company” JSC |
Implementation period | 2022-2025 |
Place of sale (city/region) | Almaty |
Industry | Digitalization |
Implementation status | in the implementation |
Objective of the project | Implementation of an intelligent electrical grid analysis and control system. |
Project Description | Determination of anomalies in calculating the level of technical power losses; Consumption forecasting; Measurement and determination of main power quality parameters; Automated Supervisory Control System for Transformer Substations (ASСS TS); calculation of distribution flow by parameters measured in real time; Application of GIS systems to determine the geographical location of TS and transmission lines |
Website | http://ceer.asia/ |
List of products sold with prices | 1. license for the Software “Intellectual System for the Analysis and Control of Power Grids” (number of contracts for the implementation of the System in pcs.) – 46,200,000 tenge, 2. technical support for the Software “Intellectual System for the Analysis and Control of Power Grids” – 8,778,000 tenge |
Project team (full name) | Baimakhanov Olzhas Saukhimov Almaz Ilyasov Azamat Bektimirov Anur Arapbekov Aibek |