Project number | AP15573707 |
Name of the project | Modification of polymer cable insulation in a protective atmosphere on the ELV-4 electron accelerator |
Applicant | JSC “Park of Nuclear Technologies” |
Grantee | “BetaIzol” LLP |
Private Partner | “Kazelectromash” LLP |
Implementation period | 2022-2024 |
Place of sale (city/region) | Abay region |
Industry | Oil and gas and chemical industry |
Implementation status | in the implementation |
Objective of the project | Introduction of advanced technology of radiation crosslinking of polymer compounds in a protective atmosphere used for the production of cable and wire products in the territory of the Republic of Kazakhstan |
Project Description | We propose a new method of modification of polymer cable insulation for the production of oil-submersible and photovoltaic cables with high performance characteristics. The project is aimed at import substitution, the creation of domestic high-tech products and new jobs. According to the assessment of manufacturers and experts in the field of cable and wire products in the markets of the EAEU member states in recent years, there has been a tendency to a decline in the quality of manufactured and consumed cable and wire products. Among the main reasons for the emergence of this trend, experts note the desire of both consumers and manufacturers to achieve maximum savings when achieving their goals within the framework of their projects. |
Website | www.betaizol.kz |
List of products sold with prices | Oil-submersible cable: KFEPs 1*4 — 423 147 tenge (per 1 km); KFEPs 1*6 — 605 983 tenge (per 1 km). Photovoltaic cable: KPvBP-130-3,3 3*16 — 7 203 545 tenge (per 1 km); KPvBP-130-4 3*16 — 7 443 495 tenge (per 1 km); KPvBP-130-3,3 3*25 — 9 815 191tenge (per 1 km); KPvBP-130-4 3*25 — 9 981 017tenge (per 1 km). |
Project team (full name) | Project Manager: Nurkassimov Azat Kanatovich Specialist in commercialization: Raspopina Alexandra Vitalievna Chief engineer of the project: Borissenko Alexander Nikolaevich Technologist: Raspopin Vitaly Leonidovich Marketer: Ershin Zeynolla Raykhanovich |